Petrochemical company with 420,000 m3 of flammable products in storage facilities

Work carried out

  • Design and Project management for the refurbishment of fuel pumping station and 6 loading islands for tanker trucks to be able to use them simultaneously with up to 3 loading arms.
  • Design and Project management for the adaptation of a 2,500 m3 jet tank to be used with FAME, including piping, pumping station, refurbishment of tank truck loading islands and heating system for the entire assembly.
  • Project and supervision of refurbishment works of a hydrocarbon-water treatment plant, to add a 90 m2 settling and aeration basin, three new filters, improvement of the remote control and new transfer possibilities between the different phases.
  • FPS refurbishment in oil facilities.